Denex Petroleum Corporation

Denex 2008-A Joint Venture

Channell No. 1 Well

(S. W. Jack Rig No. 10)
Building Location
 
 
Digging the pit.
The completed pit.
 
Rigged up, drilling hole for conductor.
(Note lack of substructure.)
 
Float equipment for surface pipe and production casing.
 
 
Air compressors at back of rig.
 
Lowering arm to pick up 8 5/8" casing.
 
Raising 8 5/8" casing.
 
Climbing derrick to "stab" casing.
 
 
Man in derrick, preparing to "stab" casing.
 
Raising 8 5/8" casing into derrick.
 
8 5/8" casing in derrick held by arm.
 
Laptop monitoring 8 5/8" cement job (wireless).
 
8 5/8" cement circulating, running to pit.
 
Logging open hole.
 
Lifting 4 1/2" casing with arm.
 
Raising casing into derrick.
 
Adding joint to string.
 
Lowering empty arm to get next joint.
 
Installing basket on casing string.
 
Logging cased hole.
 
Logging cased hole.
 
Logging cased hole.
 
Preparing perforating guns.
 
Denex pipelining equipment.
 
End of well pipeline at location.
 
Equipment on site for frac job.
 
 
 
Blender with hoppers ready for sand.
 
Sand trucks over blender.
 
Other sand trucks on location, waiting their turn.
 
Flowing well back about 11:30 PM.
 
 
Reclaimed Location (before seeding) 11/6/08