Denex Petroleum Corporation Daily Drilling Report |
| Well: Knight No. 1 | Permit No.: 47-001-02831 |
| Contractor: SW Jack Rig 19 | Spud Date: September 28, 2006 |
| District/County: Philippi/Barbour | State: West Virginia |
| Report Date: | 10/05/06 | Report Time: | 7:00 AM |
|
|
| Projected Operations (Next 24 hours): Rig down, move rig off hole. Grade road, restore drainage diversions. Haul stone. Scheduled to perforate and fracture Tuesday, October 17, 2006. |
| Thurssday, October 5, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 1:00 AM | Finished running 4 1/2" casing. |
| 1:00 AM | 2:40 AM | Cemented (Universal) casing with 570 sx of 50/50 pozmix with 2% gel, 10% salt and 1/4# flake. Pumped plug down with 500 gallons of 15% HCl acid. Landed plug at 93 bbls at about 300 psig. Bumped pressure to about 800 psig. Plug down at 2:40 AM. |
| 2:40 AM | 3:30 AM | Rig down cementers. |
| Wednesday, October 4, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 7:00 AM | Drill 7 7/8" hole. Reached TD of 5,625' at 6:55 AM. |
| 7:00 AM | 12:30 PM | Clean hole. Trip out of hole, laying down drill pipe. Prepare to log well. |
| 12:30 PM | 3:30 PM | Wait on logging truck. |
| 3:30 PM | 8:15 PM | Log well (Allegheny Wireline). |
| 8:15 PM | 11:59 PM | Ran 131 joints (5,207') of 10.5# M-60 Maverick 4 1/2" casing, with latch down in shoe on bottom, 8 centralizers (joints 1,8, 17, 22, 36, 41, 61 and 65), cement basket on joint 46 (at 3,640'), and 3 baffles (3 3/8" baffle on joint 14 at 5,010', 3 7/16" baffle on jount 37 at 4,024', and 3 9/16" baffle on joint 62 at 2,957'). |
| Tuesday, October 3, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 11:59 PM | Drill 7 7/8" hole. Rig was 4,040' at 6:50 AM, drilling about 25 minutes per kelly, dusting. Gas check at 3,981' (above Benson), no show. Rig was 4,571' at 4:00 PM, dusting, drilling 18 minutes per kelly at 4:00 PM. Gas check at 4,196', no show. Rig was 5,030' at 10:45 PM, dusting, drilling 22 minutes per kelly. Gas check at 4,724' showed 4/10ths water through 1" - about 21 mcf/day - (from Elks?). |
| Monday, October 2, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 11:59 PM | Drill 7 7/8" hole, dusting. Rig was 2,723' at 7:20 AM, drilling about 24 minutes per kelly. Gas check at 2,705', no show. Gas check at 3,202', no show. Rig was 3,578 at 11:00 PM, dusting, drilling 30 minutes per kelly. |
| Sunday, October 1, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 11:59 PM | Drill 7 7/8" hole, dusting. Rig was 1,456' at 9:50 AM, drilling about 22 minutes per kelly. Found Big Lime from 1,220' to 1,337'. Rig was 2,124' at 9:00 PM, dusting, drilling 22 minutes per kelly. |
| Saturday, September 30, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 4:00 AM | Drilling 11" hole, soaping. Reached TD of 1,000' at 3:00 AM. Cleaned hole. |
| 4:00 AM | 5:00 AM | Trip out of hole, prepare to run surface casing. |
| 5:00 AM | 6:30 AM | Ran 32 joints (972') of 8 5/8" casing (see below) with 29 joints of used casing on bottom, new casing second and third joint down, and one used joint on top. |
| 6:30 AM | 8:45 AM | Waited on cementers (Universal). Cemented casing with 265 sx of Class A cement with 3% calcium and 1/4 lb. flake. |
| 8:45 AM | 5:00 PM | Waiting on cement. |
| 5:00 PM | 8:00 PM | Nipple up, prepare to trip in hole |
| 8:00 PM | 11:25 PM | Trip in hole, blowing water. Drilled cement and plug, Started drill 7 7/8" hole. Had hole dusting at 1,030' about 11:25 PM. |
| 11:25 PM | 11:59 PM | Drilling 7 7/8" hole, dusting. |
| Friday, September 29, 2006 | ||
| From: | To: | Description of Operations |
| 12:00 AM | 11:59 PM | Tripped to change hammer bit at 378'. Rig was 434' and soaping at 8:30 AM. Rig was 434' at 1:15 PM. Rig shut down for several hours to make repairs and adjustments (mostly welding on handrails, etc.), as rig has just come from yard and major repairs. Rig is headed for upstate NY, and using this hole for "shakedown" before moving. Plan was to finish this work during top hole. Continued drilling and soaping hole. Plan to run surface casing Saturday morning during daylight hours. |
| Thursday, September 28, 2006 | ||
| From: | To: | Description of Operations |
| 5:30 AM | 10:45 PM | Spudded at 5:30 AM. Set 42.20' of 11 3/4" conductor (new 42 lb. from McJunkin) about 11:00 AM. Rig was 91 feet at 4:00 PM, dusting, drilling 11" hole with hammer. Hole got wet at 150', started soaping. Rig was 225' at 10:45, soaping. |
| Wednesday, September 27, 2006 | ||
| From: | To: | Description of Operations |
| 7:30 AM | 6:00 PM | Moved in rig. Rigged up. Prepared to spud. S. W. Jack delivered 972' of 8 5/8" casing (2 jts new 20# from McJunkin and 30 jts used 24# seamless from Denex, re-threaded by Weatherford) and 1 jt 11 3/4 (new 42# from McJunkin). |
| 6:00 PM | 10:00 PM | Worked on rig. Problem with drawworks. |
|
|
||
| From: | To: | Description of Operations |
| 8:00 AM | 4:00 PM | Graded location. |
|
|
||
| From: | To: | Description of Operations |
| 8:00 AM | 3:00 PM | Graded road, and hauled stone on road. |
|
|
||
| From: | To: | Description of Operations |
| 8:00 AM | 4:00 PM | Moved S. W. Jack dozer to location, built pit. |